Critical path scheduling

A schedule you make decisions from, not one you report with. Levels 1 to 4, critical path method, tens of thousands of activities in Primavera P6.

01When you need this
  • Contractors send schedules in different formats and at different levels of detail — merging them into one is impossible.

  • Slippage becomes visible only once it can no longer be recovered.

  • It is unclear which delay moves the completion date and which merely eats into float.

  • The bank, the investor or head office asks for a schedule in a specific standard, and there is nothing to show.

02What you get

Work breakdown structure

The project split into manageable packages by asset, stage and owner. The shared basis for schedule, budget and reporting.

Level 1–4 schedules

From the investor-level summary to the working site schedule. One project at different resolutions, with no contradictions between levels.

Baseline

The approved schedule that actuals are measured against. Without it, slippage has nothing to be compared to.

Critical path

The chain of activities that drives the completion date, and the float on everything else. It shows where a delay costs money and where it does not.

Resource and cost loading

The schedule becomes an S-curve of earned value and a period-by-period demand for labour and plant.

Update procedure

Who submits what and when, so the schedule stays alive rather than being refreshed once a quarter for a meeting.

Delay analysis

Variances traced to causes and to the party responsible — including as evidence in a dispute with a contractor.

03How the work runs
  1. 1

    Source data and WBS

    We collect design documents, contracts, quantities and construction methods, build the hierarchy and agree it with the participants.

  2. 2

    Building the schedule

    Activities, durations, logic links and constraints. The logic is checked for loops, open ends and redundant constraints.

  3. 3

    Baseline approval

    Sign-off with the participants, the baseline fixed, and the rules for changing it agreed.

  4. 4

    Update cycle

    Progress collected, schedule updated, critical path and forecast completion recalculated. Typically weekly for the site and monthly for the investor.

  5. 5

    Forecast and variance

    What happens at the current rate, what recovery options exist, and what they would cost.

What the client receives

A schedule you can look at, not one emailed as a file

The S-curve, the schedule performance index and a Gantt chart with the critical path — in a dashboard the client has access to. Exactly what the home page shows, but for your project.

See what it looks like
04Frequent questions
What is the difference between schedule levels 1 to 4?
It is one project at different resolutions. Level 1 is milestones for the investor and fits on a page. Level 2 covers stages and major assets. Level 3 is the working schedule the site runs on. Level 4 is contractor detail down to weekly and daily assignments. Lower levels must never contradict the higher ones.
Does it have to be Primavera P6? We use MS Project.
It does not. P6 earns its place on large projects with tens of thousands of activities and several contractors. On smaller projects MS Project copes. We work in both and can move the model between them.
Why formally approve a baseline?
Until the baseline is fixed, slippage is a matter of opinion. Once it is, every variance is measurable in days and money, and changes go through a procedure instead of quietly rewriting history.
How often should the schedule be updated?
Weekly for the site and monthly for investor reporting. Less often and the schedule stops reflecting reality, so people stop using it. More often and collecting the data costs more than it returns.
08Contact

Ready to take your project under control?

Tell us about the task — within 1–2 days we will prepare a team structure, a roadmap and a commercial proposal.

Send an enquiry

Describe the task — we will come back with a team structure and an initial estimate.